#10323000
Quick Facts
- Location: Town-N-Country
- Project Type: Wastewater
- Phase: Procurement
Schedule
- Planning complete: Late 2022
- Design complete:
- Construction begins: Mid 2027
- Construction complete: Early 2029
Budget Breakdown
- Total: $24,000,283
Overview
Waters Ave Forcemain Replacement. Replace 15,500 ft (2.95 miles) of 24-in force main along Waters Avenue between BJ wholesale club (7651 W Waters Ave, west of Hanley Road) and Manhattan Avenue
Objectives
To replace 15,500 ft (2.95 miles) of 24-in force main along Waters Avenue between BJ wholesale club (7651 W Waters Ave, west of Hanley Road) and Manhattan Avenue
Questions?
For more information about this project please contact (813) 635-5400 or visit At Your Service
Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.