#10323000
Quick Facts
- Location: Town and Country
- Project Type: Wastewater
- Phase: Design
Schedule
- Planning complete:
- Design complete: 12/27/2026
- Construction begins:
- Construction complete: 2/13/2029
Budget Breakdown
- Total: $26,500,000
- Design and Land: $3,858,740
- Construction: $22,641,260
Overview
- Replace 15,500 ft (2.95 miles) of 24-in force main along Waters Avenue between BJ wholesale club (7651 W Waters Ave, west of Hanley Road) and Manhattan Avenue. Project also includes sand blasting and coating pipe located on Rocky Creek Bridge and insta
Objectives
- The overview is to replace approximately 22,000 feet of the existing 24-inch force main along Waters Avenue.
Questions?
For more information about this project please contact (813) 635-5400 or visit At Your Service
Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.
Current as of 9/3/2026